With the BAK Development Centre, the Boysen Group completed its third development site in Germany in 2024 in the immediate vicinity of the BAK large-scale factory. Solutions for electromobility and in the field of environmental and energy technology are developed here. The focus here is on expanding the range of services in the field of battery housing development. The engineers in Simmersfeld are also working on innovations in the fields of hydrogen technology, fuel cell applications and the further development of stationary energy storage systems (redox flow batteries).

Milestones

July 2024Start-up of first laboratories
June 2024Completion of development and administration building
October 2022Start of construction

Floor space

Total area5,650 m²
Development and administration940 m²
Test hall1,000 m² (additional 870 m² extension area)

Facts

Employeesup to 50
Services(basic) development, design, testing and trials in the fields of fuel cells and battery systems

Key features

Chemistry laboratory for the development of active materials for electrochemical cells - in particular membranes for redox flow battery storage and fuel cells as well as catalysts for membrane electrode units
Walk-in climate and corrosion chamber for testing complete battery housings
Fuel cell test stands for single cells and stacks

Contact

Kai Kioschis / Vice President BAK Entwicklungszentrum

Tel.: +49 (0) 7484 / 9325-7410
e-mail: kai.kioschis(at)boysen-online.de

 

Address / Directions

BAK Entwicklungszentrum
Albblickstraße 6
72226 Simmersfeld